Dear Members of the Georgetown University Community,
We are reaching out to provide updates on the ongoing renovation project on Healy and Copley Lawn. This multi-year project involves replacing aging underground utilities with more energy-efficient infrastructure, contributing to Georgetown’s long-term commitment to environmental stewardship.
We encourage you to explore our landing page to learn more about the project plan, benefits and the upcoming site improvements.
Phase III
Following Reunion Weekend, we will begin Phase III of the project, which entails work in multiple zones, including into off-campus space east of the Hilltop campus. Please find descriptions of each of the zones below.
-
- June 2025 – September 2025: Healy Circle and Partial Copley Lawn (Zone A)
- This zone surrounds the John Carroll statue, taking up much of Healy Circle, and covers the south portion of Copley Lawn. During this time, the John Carroll statue will be fenced off.
- June 2025 – September 2026: Old North Way (Zone B)
- The construction fencing on Old North Way between Healy Hall and Copley Hall will remain in place until late 2026. The pedestrian pathway will continue to be available through Old North Way.
- Late Summer 2025: Lane Closure of 37th St. from O St. to Prospect St. (Zone C)
- For approximately 12 weeks, this section of 37th St. will be reduced to a single lane heading southbound. Parking in this area will be out of service during this time. Traffic delays are expected as a result of this single lane closure.
- September 2025 – November 2025: Copley Lawn (Zone D)
- During this time, the fencing previously installed on Copley Lawn during spring 2025 will return, in addition to fencing at the east corner of Red Square.
- June 2025 – September 2025: Healy Circle and Partial Copley Lawn (Zone A)
Phase III Map